ThisĀ progress chart was last updated on: 08/06/2018
Milestone | Status |
---|---|
Form a working party to develop the project | Completed |
Negotiate with UK Coal (the land owners) | Completed |
Engage consultants for the Environmental Impact Assessment (EIA) | Completed |
Agree the scope of the EIA with Wakefield council | Completed |
Negotiate with the Minerals Planning Authority (MPA) | Completed |
Establish the Workers Co-operative | Completed |
Form the Community Liaison Group | Completed |
Run Public Information Events | Completed |
Submit a planning Application | Completed |
Further negotiations with the MPA | Completed |
Full Planning consent granted by MPA | Completed |
Negotiate a contract with a coal buyer | Completed |
Raise Capital to fund the development | Completed |
Finalise Community Development Plan | In progress |
Form Community Foundation | In progress |
Appoint contractor to construct the surface infrastructure | Completed |
Construct the mine drifts to the Sharlston Top Coal Seam | Started |
Finalise Community Development Plan | Not Yet Started |
Commence mining | Not Yet Started |